Preliminary Rover Plan
Sequence 53310, Sol 33 scenario, 8/4/97

Assumptions:

Assume nominal completion of 53210 on morning of SOL 33, rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.

Now in extra special extended mission phase


52710 Rover Activities:
Time (LST) Activity Telemetry Estimate (Mbits)
~07:30 Wakeup
08:00 Morning MAE experiments
10:00 Abort Sequence 53210
10:00 S0053 of Mermaid Dune 0.5
10:00 S0050 Rover movie 0.8
10:15 Drive to entrance of Rock Garden
10:30 Image at entrance of Rock Garden 1.8
11:00 Drive into Rock Garden & position for APXS of Shark
12:00 MAE
12:30 Rover forward image of Shark 3.0
13:00 Turn around
13:15 Soil Experiment
14:00 S0055 (4 stereo pair) 1.0
15:45 Shutdown, nwith overnight APX
Sol 33 08:00 Wakeup, await new sequence (expected ~10:00)
total telemetry volume ~7.1 Mbits


Last Updated: 8/4/97