Last updated: 8 August 1997, 13:40 pm PDT
Mission Sequence Planner: ADT (Mr. T)
Rover Driver: BC
| SCET | PDT | LST | ||
|---|---|---|---|---|
| Expected uplink time: | 221 22:39 | |||
| Nominal sequence activation time: | 221 01:07:00 | Sol 35 12:30 | ||
| Nominal sequence abort time: | 222 23:49:00 | Sol 36 10:00 | (during command [35174]) |
SEQUENCE DESCRIPTION
| X Position (m) | Y Position (m) | Heading (deg) | |
|---|---|---|---|
| At Sequence Start** | -5.907 | -0.062 | 341 |
| At End of Sol 35* (predicted) | -4.592 | -2.666 | 38 |
** Vehicle positions are in surface-fixed frame
* at completion of planned SOL's traverse activities assuming nominal execution
| Image Type | X (m) | Y (m) | Z (m) |
|---|---|---|---|
| S0055 | -4.844 | -1.171 | 0.522 |
| -4.965 | -0.010 | 0.522 | |
| -12.980 | -3.466 | 0.522 | |
| -13.409 | -0.416 | 0.522 | |
| -4.096 | -2.945 | 0.522 | |
| -4.634 | -1.907 | 0.522 | |
| -10.420 | -6.959 | 0.522 | |
| -11.700 | -4.395 | 0.522 |
SEQUENCE IMPLEMENTATION REPORT
PRESS RELEASE
Web Page Author: Art Thompson
All information on this site, including text and images describing the Rover is copyright © 1997, Jet Propulsion Laboratory, California Institute of Technology and the National Aeronautics and Space Administration.