Rover Scenario
Sequence 54410, Sol 44 scenario, 8/17/97

Assumptions:

Assume that rover did not get Sol 43 sequence due to s/c reset. Sol 44 sequence will use same command seq numbers however in the event it did. Time constraints demanded removal of first image (looking past Wedge and Ren) in the SOL 43 sequence.

Assume completion of sequence 54210 runout on morning of SOL 44, rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.

Y and Z accels set to failed during initial move on SOL44. The left and right bogies and differentials are set failed during the first turn and move operations Bogies are set good for rest of traverse operations. Differential is set good for final waypoint traverse. The auto-image parameter has been disabled during SOL44 operations. There is one full stereo image scheduled to be taken during SOL44 operations. The images will be taken even if the rover errors out of its traverses.

LMRE will be powered ON at: 07:38 LST
Queue rover load 54410 at: 09:31 LST
IMP sequence S50, rover movie at: 10:00 LST
IMP sequence S56, rover EOD image at: 11:07 LST
LMRE powered OFF at: 11:07 LST


54410 Rover Activities:
Time (LST) Activity Telemetry Estimate(Mbits)
~07:15 Wakeup
09:31 Abort sequence 54210
09:38 Turn in place, move 0.53 meters
09:43 Re-enable Y accel and bogie pots, turn in place, move 0.45 meters in the +Y direction
09:48 Re-enable differential pot, waypoint traverse to Shark
10:04 Final turn toward Shark
10:07 Full stereo imaging of Shark 3.2M
10:49 Turn APXS toward Shark, straighten wheels, EOD position
11:07 LMRE off
11:51 Soil mechanics experiment
11:07 EOD imaging S0056 (8 stereo pairs) 2.0M
12:00 MAE experiment
15:45 Shutdown
--- Wake up every two hours overnight for thermal characterization
Sol 45 ~07:45 Wakeup, await new sequence
total telemetry volume ~5.2 Mbits


Last Updated: 8/17/97