Rover Scenario
Sequence 54710, Sol 47 scenario, 8/20/97

Assumptions:

Assume either sequence 54310 or 54510 may still be running, since no downlink has been available to confirm that 54510 was activated. All rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.

Try to escape gravity well of Wedge (what kinda material is it made of anyway?)


LMRE will be powered ON at: 07:38 LST
Queue rover load 54710 at: 09:31 LST
IMP sequence S0055, (not used) at: 10:33 LST
IMP sequence S0056, rover EOD image at: 10:53 LST
LMRE powered OFF at: 10:53 LST
Downlink ends at: 11:23 LST


54710 Rover Activities:
Time (LST) Activity Telemetry Estimate(Mbits)
~07:15 Wakeup
09:31 Abort sequence 54310
09:45 Get off Wedge and move toward Shark
10:23 S0056 used as EOD imaging (8 stereo pairs) 2.0
12:00 MAE experiment
14:00 MAE experiments
15:45 Shutdown
Sol 48 ~07:45 Wakeup, no uplink/downlink today (LMRE off)
Sol 48 12:00 MAE experiment
Sol 48 15:45 Shutdown
Sol 49 ~07:45 Wakeup, await new sequence
total telemetry volume ~2.5 Mbits


Last Updated: 8/20/97