Rover Scenario
Sequence 55610, Sol 56 scenario, 8/29/97

Assumptions:

Assume sequence 55510 completed nominally. Rover up on half-dome. All rover systems healthy except for failed right front wheel temperature sensors, continued noise on accels, and a flaky gyro.

Plan:

Attempt to APXS Halfdome on right side


LMRE will be powered ON at: 07:38 LST
IMP sequence S0050 (movie) at: 10:00 LST
Queue rover load 55610 at: 11:15 LST
IMP sequence S0053 at: 12:35 LST
IMP sequence S0054 at: 13:01 LST
IMP sequence S0055 at: 13:51 LST
LMRE powered OFF at: 14:01 LST
IMP sequence S0056 at: 14:01 LST
Downlink ends at: 14:28 LST


55510 Rover Activities:
Time (LST) Activity Telemetry Estimate(Mbits)
~07:15 Wakeup
11:15 Abort sequence 55510
11:30 Attemt to put APXS on right side of Halfdome
12:00 MAE experiment
12:00 Rear image of APXS deployed on Halfdome 1.0
14:00 MAE experiment
14:04 Begin APXS operations
15:45 Shutdown, APX night ops
Sol 56 ~07:45 Wakeup, await new sequence (expected 10:00 LST)
total telemetry volume ~1.3 Mbits


Last Updated: 8/29/97