Rover Scenario
Sequence 56710, Sol 67 scenario, 9/9/97

Assumptions:

Nominal completion of 56610 runout

Rover batteries DEAD :(

Plan:

APX stimpy


Sol 67 Activities Time (LST)
LMRE will be powered ON at: 07:36
Queue rover load 56710 at: 10:20
Rover movie, S0050: 10:55
Soil mech image, S0053: 12:08
Soil mech image, S0054: 12:55
EOD image, S0055: 13:43
Rover tracks image, S0056: 14:04
LMRE off: 14:07
Downlink Ends 14:31
Sol 68
LMRE will be powered ON at: 07:36
Queue rover load 56810 at: 09:38
LMRE off: 14:10
Downlink Ends 14:30


Sol 67 Rover Activities:
Time (LST) Activity Telemetry Estimate(Mbits)
~07:30 Solar Wakeup
10:20 Abort sequence 56610
10:55 Drive to stimpy
10:55 Rover movie (S0050)
11:00 APX post deploy site image 1.0
12:00 MAE experiment
12:00-13:30 APXS data collection on Stimpy
13:30-14:30 APXS data collection on Stimpy
13:50 End of day image (as S0055) 1.5
14:30 Shutdown
Sol 68
~07:30 Solar Wakeup
08:00-09:00 APXS data collection on Stimpy
09:00-09:30 APXS data collection on Stimpy
09:30-10:00 Possible new sequence
10:00-10:30 APXS data collection on Stimpy
10:30-11:00 APXS data collection on Stimpy
12:00 MAE experiment
12:00-13:30 APXS data collection on Stimpy
13:30-14:30 APXS data collection on Stimpy
14:30 Shutdown
Sol 69
~07:30 Solar Wakeup
08:00-09:00 APXS data collection on Stimpy
09:00-09:30 APXS data collection on Stimpy
09:30-10:00 Await new sequence (nominal 09:30)
total telemetry volume ~4.0 Mbits


Last Updated: 9/9/97