Rover Scenario
Sequence 57510, Sol 75 scenario, 9/18/97

Assumptions:

Rover has executed Sol 74 sequence 57410 until nominal end of sequence. Rover is healthly, ready to continue its imaging trek.

Plan:


Sol 75 Activities Time (LST)
LMRE will be powered ON at: 07:38
Queue rover load 57510 at: 10:20
Soil mech image, S0054: 11:30
EOD image, S0055: 11:28
LMRE off: 11:53 (short day)
Downlink Ends 12:28
Sol 76
LMRE will be powered ON at: 07:38
Rover imageing back side of the dune 08:30
Queue rover load 57610 at: 09:37
LMRE off: 11:25
Downlink Ends 12:00 (shorter day)


Last Updated: 9/18/97