Preliminary Rover Plan
51310?, Sol 13 scenario, 7/16/97

Assumptions:

Assume nominal completion of 51210 on SOL 12, all rover systems healthy.


Time (LST) Activity Telemetry Estimate
7:00 Wakeup
10:00 Move to soil mechanics site
10:15 5.05 Basline Soil Mechanics with S0053 & S0054 ~1.5Mbits (+ ~1.0Mbits IMP)
11:00 Move toward Scooby-Doo (~20cm in front of) with S0050
12:00 MAE
12:00 Front uncompressed stereo images of Scooby 6.0 Mbits
13:00 Modified Soil Mechanics (no rover imaging) with S0354 (~0.5 Mbits IMP)
13:30 Turn around
13:45 Rear color image (subframe) ~1.0 Mbits
14:00 MAE
>14:00 S0055 (4 stereo pair)
16:00 Shutdown, no night ops
total telemetry volume ~9.0 Mbits


Last Updated: 7/16/97