Assumptions:
Assume nominal runout of 51510 on SOL 16/17, all rover systems healthy.
Plan four days of runout (through morning of Sol 21) while lander
debugs com problems.
51710B Rover Activities:
- Abort sequence 51510B (~07:00)
- Perform MAE experiment (~12:00)
- Perform MAE experiment (~14:00)
- Shutdown (~16:00)
- Wake up ~07:00 on SOL 18
- Await new sequence
All times LST unless otherwise specified
Last Updated: 7/20/97