STATUS: DONE


FLIGHT REPORT

Sol 18
ROVER SEQUENCE PLANNING REPORT


Last updated: 21 July 1997, 4:30 pm PDT
Mission Sequence Planner: RW/AHM
Rover Driver: JM/BC




ROVER SEQUENCE ID: 51810D

SCETPDTLST
Expected uplink time:
Nominal sequence activation time:203 11:21:0010:00
Nominal sequence abort time:204 08:55:00Sol 19 07:00(during command [18127])

Previous sequence 51710C will nominally be aborted at command [17058]




MISSION SEQUENCE PLANNER REPORT




SEQUENCE DESCRIPTION




SEQUENCE IMPLEMENTATION REPORT




SCIENCE/TECHNOLOGY OBJECTIVES REPORT