Preliminary Rover Plan
Sequence 52610, Sol 26 scenario, 7/29/97

Assumptions:

Assume nominal completion of 52510 on morning of SOL 26, rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.


52610 Rover Activities:
Time (LST) Activity Telemetry Estimate
~07:00 Wakeup
07:30 Abort sequence 52410D
12:00 MAE
15:45 Shutdown, no night ops
rover telemetry volume ~9.0 Mbits


Last Updated: 7/28/97