Preliminary Rover Plan
Sequence 52710, Sol 27 scenario, 7/30/97

Assumptions:

Assume nominal completion of 52610 on morning of SOL 27, rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.


52710 Rover Activities:
Time (LST) Activity Telemetry Estimate (Mbits)
08:00 Wakeup
08:00 Morning MAE experiments
10:00 Abort Sequence 52610
10:15 Backup into Mermaid Maid Dune (rover movie???) 1.0
10:30 WAE wheelie experiment with IMP image (S0054?) 0.5
12:00 MAE
12:00 APX site image (rear camera) 1.0
12:30 Deploy APX
13:00 Rover EOD ops images (lander engineering image?) 1.2
14:00 S0055 (4 stereo pair) 1.0
15:45 Shutdown, nwith overnight APX
Sol 28 08:00 Wakeup, await new sequence (expected ~10:00)
toatl telemetry volume ~5.0 Mbits


Last Updated: 7/30/97