STATUS: DONE


FLIGHT REPORT

Sol 27
ROVER SEQUENCE PLANNING REPORT


Last updated: 30 July 1997, 10:00 pm PDT
Mission Sequence Planner: AHM
Rover Driver: JM




ROVER SEQUENCE ID: 52710D

SCETPDTLST
Expected uplink time:
Nominal sequence activation time:212 17:15:0010:00
Nominal sequence abort time:213 17:55:00Sol 28 10:00(during command [27165])

Previous sequence 52610B will nominally be aborted at command [26164]




MISSION SEQUENCE PLANNER REPORT




SEQUENCE DESCRIPTION




SEQUENCE IMPLEMENTATION REPORT




SCIENCE/TECHNOLOGY OBJECTIVES REPORT