Preliminary Rover Plan
Sequence 53210, Sol 32 scenario, 8/4/97

Assumptions:

Assume nominal completion of 53010 on morning of SOL 32, rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.

Now in extra special extended mission phase


52710 Rover Activities:
Time (LST) Activity Telemetry Estimate (Mbits)
07:30 Wakeup
08:00 Morning MAE experiments
10:00 Abort Sequence 53010
12:00 MAE
13:00 Rover EOD ops images (lander engineering image?) 1.2
14:00 S0055 (4 stereo pair) 1.0
15:45 Shutdown, nwith overnight APX
Sol 33 08:00 Wakeup, await new sequence (expected ~10:00)
total telemetry volume ~5.0 Mbits


Last Updated: 8/2/97