Last updated: 9 August 1997, 10:40 pm PDT
Mission Sequence Planner: AHM
Rover Driver: BC
| SCET | PDT | LST | ||
|---|---|---|---|---|
| Expected uplink time: | 221 21:06 | |||
| Nominal sequence activation time: | 221 23:10:00 | Sol 36 10:00 | ||
| Nominal sequence abort time: | 222 23:49:00 | Sol 37 10:00 | (during command [36176]) |
SEQUENCE DESCRIPTION
| X Position (m) | Y Position (m) | Heading (deg) | |
|---|---|---|---|
| At Sequence Start** | -3.498 | -0.885 | 91 |
| At End of Sol 36* (predicted) | -4.810 | -2.735 | 42 |
** Vehicle positions are in surface-fixed frame
* at completion of planned SOL's traverse activities assuming nominal execution
| Image Type | X (m) | Y (m) | Z (m) |
|---|---|---|---|
| S0055 | -4.844 | -1.171 | 0.522 |
| -4.965 | -0.010 | 0.522 | |
| -12.980 | -3.466 | 0.522 | |
| -13.409 | -0.416 | 0.522 | |
| -4.096 | -2.945 | 0.522 | |
| -4.634 | -1.907 | 0.522 | |
| -10.420 | -6.959 | 0.522 | |
| -11.700 | -4.395 | 0.522 |
SEQUENCE
IMPLEMENTATION REPORT