STATUS: Completed


FLIGHT REPORT

Sol 42
ROVER SEQUENCE PLANNING REPORT


Last updated: 15 August 1997, 18:30 PDT
Mission Sequence Planner: A Thompson (Mr. T)
Rover Driver: B. Cooper (Dude)




ROVER SEQUENCE ID: 54210D

SCETLST
Expected uplink time:228 01:37Sol 42 08:00
Nominal sequence activation time:228 02:17Sol 42 09:37
Nominal sequence abort time:229 02:46Sol 43 10:05(during command [42125])

Previous sequence 54110 will nominally be aborted at command [40111]




MISSION SEQUENCE PLANNER REPORT




SEQUENCE DESCRIPTION




SEQUENCE IMPLEMENTATION REPORT


See Notes to Rover Team above.



SCIENCE/TECHNOLOGY OBJECTIVES REPORT





PRESS RELEASE


  • The rover will attempt to drive out of a patch of rocks and head toward the rock called Shark. We expect to take two days of driving to reach Shark. The rover has been unable to complete drives for the last few days due to the very rocky terrain.


    Web Page Author: Art Thompson

    All information on this site, including text and images describing the Rover is copyright © 1997, Jet Propulsion Laboratory, California Institute of Technology and the National Aeronautics and Space Administration.