Rover Scenario
Sequence 54310, Sol 43 scenario, 8/16/97

Assumptions:

Assume nominal completion of sequence 54210 on morning SOL SOL 43, rover systems healthy except for failed right front wheel temperature sensors and continued noise on accels.

Y and Z accels set to failed during initial move on SOL43. The left and right bogies and differentials are set failed during the first turn and move operations Bogies are set good for rest of traverse operations. Differential is set good for final waypoint traverse. The auto-image parameter has been disabled during SOL43 operations. There are two full stereo images scheduled to be taken during SOL43 operations. The images will be taken even if the rover errors out of its traverses.

LMRE will be powered ON at: 07:38 LST
Queue rover load 54310 at: 10:05 LST
IMP sequence S50, rover movie at: 09:59 LST
IMP sequence S56, rover EOD image at: 11:54 LST
LMRE powered OFF at: 11:50 LST


54310 Rover Activities:
Time (LST) Activity Telemetry Estimate(Mbits)
~07:15 Wakeup
10:05 Abort sequence 54210
10:14 Turn in place, move 0.53 meters
10:20 Re-enable Y accel and bogie pots, turn in place, move 0.45 meters in the +Y direction
10:10 Front stereo imaging of rock garden
10:45 Re-enable differential pot, waypoint traverse to Shark
11:01 Final turn toward Shark
11:05 Full stereo imaging of Shark
11:47 Turn APXS toward Shark, straighten wheels, EOD position
11:50 LMRE off
11:51 Soil mechanics experiment
11:54 EOD imaging S0056 (8 stereo pairs)
12:00 MAE experiment
15:45 Shutdown
--- Wake up every two hours overnight for thermal characterization
Sol 42 ~07:45 Wakeup, await new sequence
total telemetry volume ~5.3 Mbits


Last Updated: 8/16/97