Rover Scenario
Sequence 57310, Sol 73 scenario, 9/16/97

Assumptions:

Nominal completion of 57210, moving toward chimp

Plan:

Imagimg of chimp and other far off rocks


Sol 73 Activities Time (LST)
LMRE will be powered ON at: 07:38
Queue rover load 57310 at: 10:00
Rover movie, S0050: 10:30
Soil mech image, S0053: 10:50
Soil mech image, S0054: 11:10
EOD image, S0055: 12:43
Rover tracks image, S0056: 13:13
LMRE off: 13:07
Downlink Ends 13:43
Sol 74
LMRE will be powered ON at: 07:38
Queue rover load 56810 at: 09:31
LMRE off: 11:53
Downlink Ends 13:26


Sol 73 Rover Activities:
Time (LST) Activity Telemetry Estimate(Mbits)
~07:30 Solar Wakeup
10:00 Abort sequence 57210
10:05 Move closer to chimp
10:10 Close-up science images of imp 2.6
10:45 Drive behind chimp to get close to swale
11:30 Soil Mechanics
12:00 MAE experiment
12:05 imaging of swale 3.0
12:43 End of day image (as S0055) 1.5
14:30 Shutdown
Sol 74
~07:30 Solar Wakeup, await new sequence
total telemetry volume ~8.0 Mbits


Last Updated: 9/16/97