Last updated: 09/23/97
|
| SCET | PDT | LST | ||
|---|---|---|---|---|
| Nominal sequence activation time: | 267-04:50 | SOL 80-09:31 | ||
| Nominal sequence abort time: | 269-05:20 | SOL 81-09:42 | (during command [30126]) |
Previous sequence 57910B will nominally be aborted at command [29123]
MISSION SEQUENCE PLANNER REPORT
SEQUENCE DESCRIPTION
Plan:
Upload patch for contigency primary mission. Contiune APX of chimp through morning of Sol 81.
| Sol 80 Activities | Time (LST) |
|---|---|
| Solar Wakeup | ~07:30 |
| LMRE will be powered ON at: | 08:10 |
| Queue rover load 58010 at: | 10:35 |
| LMRE off: | 10:41 (ACK!!!) |
| EOD image, (use S0055): | 10:15 |
| Downlink Ends | 11:16 |
| MAE | 12:00 |
| Afternoon APX | 12:00-14:30 |
| Shutdown | 14:30 |
| Sol 81 Activities | |
| Solar Wakeup | ~07:30 |
| LMRE will be powered ON at: | 08:10 |
| Morning APX | 08:00-09:30 |
| Queue rover load 58110 at: | 9:42 |
| Await new sequence | 9:42 (expected) |
| LMRE off: | 10:05 (ack!) |
No end of day image in Sol 79 to localize rover position, no motion planned for Sol 80
| X Position (m) | Y Position (m) | Heading (deg) | |
|---|---|---|---|
| At Sequence Start** | ??? | ??? | ??? |
| At End of Sol 80* (predicted) | ??? | ??? | ??? |
** Vehicle positions are in surface-fixed frame
* at completion of planned SOL's traverse activities assuming nominal execution
| Image Type | X (m) | Y (m) | Z (m) |
|---|---|---|---|
| S0055 | -20.0 | 0.66 | 0.145 |
| S0055 | -19.65 | -3.90 | 0.145 |
SCIENCE/TECHNOLOGY OBJECTIVES REPORT