Last updated: 20 July 1997, 11:00 am PDT
Mission Sequence Planner: RW/AHM
Rover Driver: BC/JM
| SCET | PDT | LST | ||
|---|---|---|---|---|
| Expected uplink time: | ||||
| Nominal sequence activation time: | 202 7:35:00 | Sol 17 07:00 | ||
| Nominal sequence abort time: | 203 08:15:00 | Sol 18 07:00 |
Previous sequence 51510B will nominally be aborted at command []
MISSION SEQUENCE PLANNER REPORT
SEQUENCE DESCRIPTION
No motion planned
No imaging requested
Sol 17 Downlink (by APID)
Small amount of engineering data and MAE data generated.
SEQUENCE IMPLEMENTATION REPORT
Proceed with nominal sequence Operational Constraints:
SCIENCE/TECHNOLOGY OBJECTIVES REPORT